$~21 * IN THE HIGH COURT OF DELHI AT NEW DELHI + ARB.P. 107/2019 M/S R K BARARIA THROUGH: SHRI R K BARARIA PROP. ..... Petitioner Through:

Mr.Sanjay Bansal, Adv.

versus M/S NANDI INFRATECH PVT. LTD.

..... Respondent Through:

None.

CORAM:

HON'BLE MR. JUSTICE NAVIN CHAWLA

O R D E R

% 14.02.2019 I.A. No.2299/2019 (Exemption) Allowed, subject to all just exceptions.

ARB.P.107/2019 Upon being confronted that Clause 30 of the General Conditions of the Contract of the Construction Agreement dated 31.01.2015 does not constitute an Arbitration Agreement between the parties, learned counsel for the petitioner seeks leave to withdraw the present petition with liberty to take appropriate remedy for redressal of the grievance of the petitioner. The petition is dismissed as withdrawn with liberty as prayed for. NAVIN CHAWLA, J FEBRUARY 14, 2019/Arya