M/S Amar Construction v. Government Of NCT Of Delhi
$~77 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P.(MISC.)(COMM.) 258/2026 M/S AMAR CONSTRUCTION .....Petitioner Through:
Mr. Rajeev Kumar, Adv.
versus GOVERNMENT OF NCT OF DELHI .....Respondent Through:
Mr. Bharat Singh Sisodia, Adv.
(through VC)
CORAM:
HON'BLE MR. JUSTICE AVNEESH JHINGAN
O R D E R
% 23.03.2026 1.
This petition is filed under Section 29A of the Arbitration & Conciliation Act, 1996 seeking extension of period for concluding the arbitration proceedings.
2.
Learned counsel for the respondent has no serious objection to the prayer made.
3.
In view of the above, the time period for conclusion of the proceedings is extended by six months as prayed for. 4.
This petition is disposed of in the aforesaid terms. AVNEESH JHINGAN, J MARCH 23, 2026 'ha'