$~31 * IN THE HIGH COURT OF DELHI AT NEW DELHI + ARB.P. 123/2019 M/S PEE JAY ENGINEERING WORKS ..... Petitioner Through:

Mr. Rakesh Kumar with Ms. Preeti Kashyap, Mr. Aashish Khattar and Ms. Zinnea Mehta, Advocates versus M/S DIAMOND INTERNATIONAL PRIVATE LIMITED & ANR.

..... Respondents Through:

None.

CORAM:

HON'BLE MR. JUSTICE RAJIV SHAKDHER

O R D E R

% 21.02.2019 I.A. No. 2711/2019 (Exemption) 1.

Allowed, subject to just exceptions.

I.A. No. 2712/2019 (Delay of 4 days in re-filing) 2.

For the reasons given in the application, the delay in re-filing is condoned.

3.

The application is disposed of.

ARB.P. 123/2019 4.

After some arguments, counsel for the petitioner seeks to withdraw the captioned petition with liberty to take recourse to an appropriate remedy under the Arbitration and Conciliation Act, 1996 in respect of appointment of the Arbitrator made by the respondent including laying a challenge to his appointment.

ARB.P. 123/2019

5.

The petition is dismissed as withdrawn with liberty as prayed for. RAJIV SHAKDHER, J.

FEBRUARY 21, 2019 c ARB.P. 123/2019