Rani Construction Pvt Ltd v. Ministry Of Road Transport And Highways New Delhi
$~58 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P.(MISC.)(COMM.) 276/2026 RANI CONSTRUCTION PVT LTD .....Petitioner Through:
Mr. Sanjay Mani Tripathi, Ms.
Saumya Shikha & Mr.
Mrinal Tripathi, Advs.
versus MINISTRY OF ROAD TRANSPORT AND HIGHWAYS NEW DELHI .....Respondent Through:
Mr. Apoorv Shukla, CGSC with Mr.
Aishani Narain, GP.
CORAM:
HON'BLE MR. JUSTICE AVNEESH JHINGAN
O R D E R
% 12.05.2026 1.
This petition is filed under Section 29A of the Arbitration & Conciliation Act, 1996 seeking extension of period for concluding the arbitration proceedings.
2.
Learned counsel for the respondent has no serious objection to the prayer made.
3.
In view of the above, the time period for conclusion of the proceedings is extended by six months.
4.
This petition is disposed of in the aforesaid terms. AVNEESH JHINGAN, J MAY 12, 2026/'JK'
The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 15/05/2026 at 12:36:37