← Library
High Court of DelhiO.M.P.(MISC.)(COMM.)/75/2019

Predominant Engineers And Contractors Pvt. Ltd. v. Trimula Industries Ltd.

2019-02-22Hon'Ble Mr. Justice Navin Chawla1 pages

$~14 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P.(MISC.)(COMM.) 75/2019 PREDOMINANT ENGINEERS AND CONTRACTORS PVT. LTD. ..... Petitioner Through: Mr.Nishant Kumar Srivastava, Adv.

versus TRIMULA INDUSTRIES LTD.

..... Respondent Through: Ms.Charu Sangwan, Adv.

CORAM:

HON'BLE MR. JUSTICE NAVIN CHAWLA

O R D E R

% 22.02.2019 IA 2796/2019 Exemption allowed subject to all just exceptions. OMP(MISC.) (COMM) 75/2019 This petition under Section 29A of the Arbitration and Conciliation Act, 1996 has been filed by the petitioner seeking extension of time for the Sole Arbitrator to pass the Award.

Counsel for the respondent who appears on an advance notice submits that the respondent has no objection if the time for making of the Award is extended by this Court.

Having considered the contents of the petition and no objection expressed by the counsel for the respondent, the time for making of the Award by the Sole Arbitrator is extended till 31.12.2019. The petition is allowed in the above terms with no order as to costs. Dasti.

NAVIN CHAWLA, J FEBRUARY 22, 2019 RN