Centre For Indian Classical Dance v. Pujas Shilpkala Pvt Ltd
$~73 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P.(MISC.)(COMM.) 219/2025 CENTRE FOR INDIAN CLASSICAL DANCE .....Petitioner Through:
Mr. Alok Kumar, Sr. Advocate with Ms. Manisha A. Narain, Mr Amit Kumar Singh, Mr Varun Maheshwari Mr. Manan Soni, Advocates versus PUJAS SHILPKALA PVT LTD .....Respondent Through:
Appearance not given.
CORAM:
HON'BLE MR. JUSTICE SUBRAMONIUM PRASAD
O R D E R
% 20.03.2025 I.A. 6467/2025 (Exemption) Allowed, subject to all just exceptions.
O.M.P.(MISC.)(COMM.) 219/2025 1.
This petition under Section 29A of the Arbitration and Conciliation Act, 1996 has been filed by the Petitioner for extending the mandate of the Arbitral Tribunal.
2.
Material on record indicates that the Petitioner had approached this Court by filing an arbitration petition being ARB.P. 383/2013 for appointment of an Arbitrator and this Court vide Order dated 27.09.2017 constituted an Arbitral Tribunal consisting of a Sole Arbitrator. Pleadings stood completed. It is stated that the parties had extended the mandate of the Arbitral Tribunal by mutual consent for a period of six months w.e.f. The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 26/03/2025 at 14:03:31
06.11.2018 to 06.05.2019. The mandate of the Arbitral Tribunal has been extended periodically by this Court and the last of the mandate of the Arbitral Tribunal has been extended by this Court till 08.03.2025 vide Order dated 09.09.2024. The mandate of the Arbitral Tribunal has expired on 08.03.2025.
3.
It is stated that final arguments are being advanced before the Arbitral Tribunal.
4.
Learned Counsel appearing for the Respondent has no objection if the mandate of the Arbitral Tribunal is extended. 5.
The Apex Court in Rohan Builders (India) Private Limited v. Berger Paints India Limited, 2024 SCC OnLine SC 2494, has held that an application for extension of the time period for passing an arbitral award under Section 29A(4) read with Section 29A(5) is maintainable even after the expiry of the twelve-month or the extended six-month period, as the case may be.
6.
In view of the facts of the present case, this Court is inclined to regularize the mandate of the Arbitral Tribunal till today and the mandate is extended till 30.11.2025 so that the Award can be pronounced. 7.
The petition is disposed of, along with the pending applications, if any.
SUBRAMONIUM PRASAD, J MARCH 20, 2025 S. Zakir The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 26/03/2025 at 14:03:31