High Court of DelhiO.M.P.(MISC.)(COMM.)/290/2026

M/S Pink City Expressway Pvt. Ltd. v. National Highway Authority Of India ( Nhai)

2026-04-02Hon'Ble Mr. Justice Avneesh Jhingan1 pages

$~59 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P.(MISC.)(COMM.) 290/2026 M/S PINK CITY EXPRESSWAY PVT. LTD.

.....Petitioner Through:

Mr. Sidhant Dwibedi and Mr. Manoj Kumar, Advs.

versus NATIONAL HIGHWAY AUTHORITY OF INDIA ( NHAI) .....Respondent Through:

Mr. Ankur Mittal, Mr. Abhay Gupta, Mr. Ankur Sabud and Mr. Hrithik Saxena, Advs.

CORAM:

HON'BLE MR. JUSTICE AVNEESH JHINGAN

O R D E R

% 02.04.2026 1.

This petition is filed under Section 29A of the Arbitration & Conciliation Act, 1996 seeking extension of period for concluding the arbitration proceedings.

2.

Learned counsel for the respondent has no serious objection if mandate of the arbitrator is extended by twelve months. 3.

In view of the above, the time period for conclusion of the proceedings is extended by twelve months.

4.

This petition is disposed of in the aforesaid terms. AVNEESH JHINGAN, J APRIL 2, 2026/PA The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 06/04/2026 at 13:06:19