Punj Lloyd Ltd. Through Liqudiator v. Dy. Chief Engineer (Construction-Ii) North Western Railway
$~64 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P.(MISC.)(COMM.) 217/2024 PUNJ LLOYD LTD. THROUGH LIQUDIATOR ..... Petitioner Through:
Mr Udita Singh and Mr Sachin Bajpai, Advs.
versus DY. CHIEF ENGINEER (CONSTRUCTION-II) NORTH WESTERN RAILWAY ..... Respondent Through:
Mr Om Prakash, Adv. (through VC) with Ms Swati Mishra and Mr Chandresh Pratap, Advs. for NWR Mr Mahamaya Chatterjee, Govt.
Pleader with Mr. Aayush Agrawal, Adv. (through VC)
CORAM:
HON'BLE MR. JUSTICE JASMEET SINGH
O R D E R
% 05.04.2024 1.
This is a petition under Section 29A(4) and 29A(5) of the Arbitration & Conciliation Act, 1996 seeking extension of time of six months for the learned Arbitrator to conclude the arbitration proceedings and pass the award.
2.
It is stated that the matter is at the stage of final hearing and the evidence took some time.
3.
Ms Mishra, learned counsel appears on behalf of the respondent and has handed over a letter dated 04.04.2024 from the respondent giving no objection to the petition being allowed.
The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 10/04/2024 at 12:30:17
4.
For the said reasons, the petition is allowed. The time for concluding the arbitration proceedings and passing the Award is extended upto 24.12.2024.
5.
The petition is disposed of accordingly.
6.
The letter dated 04.04.2024 handed over in Court today is taken on record.
JASMEET SINGH, J APRIL 5, 2024 sr Click here to check corrigendum, if any The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 10/04/2024 at 12:30:17