$~O-38 * IN THE HIGH COURT OF DELHI AT NEW DELHI + CS(COMM) 92/2020 SORIN GROUP ITALIA S.R.L .....Plaintiff Through:

Ms. Ananya Kumar, Mr. Utkarsh Khandelwal and Mr.

Kamaljeet Singh, Advs.

versus NEERAJ GARG .....Defendant Through:

Mr. Rohan Jaitley, Mr. Akshay Sharma and Mr. Dev Pratap Shahi, Advs.

CORAM:

HON'BLE MR. JUSTICE PURUSHAINDRA KUMAR KAURAV

O R D E R

% 29.08.2025 I.A. 21316/2025 (filed on behalf of the plaintiff to take on record the settlement agreement dated 05.08.2025) 1.

Learned counsel appearing for the plaintiff has filed the instant petition to take on record the settlement agreement dated 05.08.2025. 2.

Application stands allowed and disposed of.

CS(COMM) 92/2020 1.

The settlement agreement has been perused and the same conforms with the legal requirement as envisaged under Order XXIII, Rule 3 of the CPC.

2.

Order XXIII, Rule 3 authorises the Court to pass a decree on a compromise wherein the parties to the dispute have made an arrangement to settle the dispute. It has been comprehensively stated in the provision that The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 02/09/2025 at 12:31:29

the settlement arrived at should meet the essentials laid down therein, namely, (i) the compromise is lawful (ii) it is reduced in writing (iii) it is duly signed by the parties arriving at the compromise. 3.

The settlement has been agreed upon without fear or coercion and the parties appear to have entered into the settlement agreement on their own volition.

4.

The Court is satisfied that the settlement has been arrived at between the parties following due procedure and meeting the essentials specified Order XXIII, Rule 3. Therefore, the parties shall be bound by the aforesaid settlement agreement.

5.

The suit stands decreed in terms of the settlement. 6.

Suit stands disposed of.

7.

The date already fixed i.e. 09.10.2025, stands cancelled. PURUSHAINDRA KUMAR KAURAV, J AUGUST 29, 2025/P/MJ The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 02/09/2025 at 12:31:29