Dalip Kumar Sharma v. Mcd, Through Its Commissioner And ORS.
$~51 *
IN THE HIGH COURT OF DELHI AT NEW DELHI
+ W.P.(C) 4734/2026 & CM APPL. 23124-23125/2026 DALIP KUMAR SHARMA .....Petitioner Through:
Mr.
Colin Gonsalves, Senior Advocate with Ms. Aly Mirza and Mr.
Mohammad Tanvir Ali, Advocates.
versus MCD, THROUGH ITS COMMISSIONER AND ORS.
.....Respondents Through:
Ms. Harita Mehta, Advocate for MCD (through VC).
Mr. Abhishek Yadav, SPC for R-2/ Delhi Police.
SI Amit Rathee, PS: Lahori Gate.
CORAM:
HON'BLE MR. JUSTICE AMIT BANSAL
O R D E R
% 13.04.2026 1.
The present writ petition has been filed seeking a direction to the respondents no.1 and 2 to restrain respondents no.3 and 4 from undertaking any illegal and unauthorized construction/demolition in property bearing no.18-22, Gandhi Gali, Fatehpuri, Delhi-110006 (hereinafter 'subject property').
2.
It is contended on behalf of the petitioner that there is a common wall which separates the subject property from the property of the petitioner and if demolition exercise is carried out, it will affect the structural integrity of the wall and grave damage would be caused to the property of the petitioner. W.P.(C) 4734/2026 The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 16/04/2026 at 13:15:47
3.
A work-stop notice had been issued by respondent no.1/MCD to respondent no.2 on 1st May, 2025 directing stopping of any unauthorized construction at the subject property.
4.
Counsel appears on behalf of respondent no.2/SHO, Police Station: Lahori Gate and submits that no demolition exercise is being carried out in the subject property. He submits that a few days back, some material had dropped from the roof top of the subject building. 5.
In view of the aforesaid submissions, the present writ petition is disposed of while directing respondents no.1 and 2 to ensure that the structural integrity of the wall marked with red colour on the site plan (at Annexure-P1) of the subject property is not compromised, weakened or demolished by any action of the private respondents. 6.
All pending applications are disposed of accordingly. AMIT BANSAL, J APRIL 13, 2026 Rzu W.P.(C) 4734/2026 The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 16/04/2026 at 13:15:47