High Court of DelhiARB.P./395/2024

M/S Zagson Engineering Ltd v. Doosan Power System India Pvt Ltd

2024-10-09Hon'Ble Mr. Justice Jasmeet Singh1 pages

$~1 * IN THE HIGH COURT OF DELHI AT NEW DELHI + ARB.P. 395/2024 M/S ZAGSON ENGINEERING LTD .....Petitioner Through:

Mr. Faiyaz Hasan, Adv.

versus DOOSAN POWER SYSTEM INDIA PVT LTD .....Respondent Through:

Mr. Deepak Khurana, Mr. Bhaskar, Advs.

CORAM:

HON'BLE MR. JUSTICE JASMEET SINGH

O R D E R

% 09.10.2024 1.

In view of the objection raised by Mr. Khurana, learned counsel for the respondent regarding the arbitration clause being subject to ICA jurisdiction, Mr. Hasan, learned counsel for the petitioner seeks to withdraw the present petition with liberty to take appropriate steps in accordance with law.

2.

Granting the said liberty, the present petition is dismissed as withdrawn.

JASMEET SINGH, J OCTOBER 9, 2024 / (MS) Click here to check corrigendum, if any The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 02/07/2025 at 00:26:05