Buniyad Construction Pvt. Ltd. v. Embassy Of Democratic Republic Of Congo
$~48 * IN THE HIGH COURT OF DELHI AT NEW DELHI + OMP (ENF.) (COMM.) 53/2019 BUNIYAD CONSTRUCTION PVT. LTD.
.....Decree Holder Through:
Mr Varun Sharma, Adv. (through VC) versus EMBASSY OF DEMOCRATIC REPUBLIC OF CONGO .....Judgement Debtor Through:
Mr Tejas Karia, Adv. (through VC) with Mr Prakhar Deep, Mr Nishant Doshi and Mr Nitin Sharma, Advs.
CORAM:
HON'BLE MR. JUSTICE JASMEET SINGH
O R D E R
% 09.09.2024 EX.APPL.(OS) 1440/2024 1.
This is an application seeking restoration of the captioned execution petition as the balance amount as directed in the order dated 29.05.2024 has not been paid.
2.
It is stated that the demand draft was prepared for the said amount but the demand draft had expired and could not be renewed. 3.
Since the amount is lying in the Bank, it is directed that a sum of Rs.1,37,78,096/- be released via electronic transfer within two working days by the Manager, RBL Bank, Branch: Vasant Vihar (0182) in favour of Buniyad Constructions Private Limited, Indian Bank, Preet Vihar, A/C No. 6484235697, IFSC: IDIB000P156.
4.
The application is disposed of in the aforesaid terms. 5.
Dasti.
JASMEET SINGH, J SEPTEMBER 9, 2024/sr Click here to check corrigendum, if any The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 10/09/2024 at 12:14:38