Vasdev v. Union Of India Through General Manager Nr
$~24 *
IN THE HIGH COURT OF DELHI AT NEW DELHI
+ ARB.P. 572/2025 VASDEV .....Petitioner Through:
versus UNION OF INDIA THROUGH GENERAL MANAGER NR .....Respondent Through:
CORAM:
HON'BLE MR. JUSTICE JASMEET SINGH
O R D E R
% 26.05.2025 1.
This is a petition filed under Section of Arbitration and Conciliation Act, 1996 seeking appointment of an arbitrator to adjudicate the disputes between the parties.
2.
In the present case, the parties entered into an Agreement dated 27.12.2018 for work of one additional third floor over Anand Vihar Station.
3.
The said Agreement contained an arbitration clause being Clause No. 64 of GCC which reads as under:- "64.(1) Demand For Arbitration :
64.(1) (i) In the event of any dispute or difference between the parties hereto as to the Construction or operation of this contract, or the respective rights and liabilities of the parties on any matter in question, dispute or difference on The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
any account or as to the withholding by the Railway of any certificate to which the contractor may claim to be entitled to, or if the Railway fails to make a decision within 120 days, then and in any such case, but except in any of the "excepted matters" referred to in Clause 63 of these Conditions, the contractor, after 120 days but within 180 days of his presenting his final claim on disputed matters shall demand in writing that the dispute or difference be referred to arbitration.
64.(1) (ii) (a)The demand for arbitration shall specify the matters which are in question, or subject of the dispute or difference as also the amount of claim item-wise. Only such dispute(s)or difference(s) in respect of which the demand has been made, together with counter claims or set off, given by the Railway, shall be referred to arbitration and other matters shall not be included in reference. 64.(1) (ii) (b) The parties may waive off the applicability of sub-section 12(5) of Arbitration and Conciliation (Amendment) Act 2015, if they agree for such waiver, in writing, after dispute having arisen between them, in the format given under Annexure XII of these conditions. 64.(1) (iii) (a) The Arbitration proceedings shall be assumed to have commenced from the day, a written and valid demand for arbitration is received by the Railway. (b) The claimant shall submit his claim stating the facts supporting the claims alongwith all the relevant documents The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
and the relief or remedy sought against each claim within a period of 30 days from the date of appointment of the Arbitral Tribunal.
(c) The Railway shall submit its defence statement and counter claim(s), if any, within a period of 60 days of receipt of copy of claims from Tribunal thereafter, unless otherwise extension has been granted by Tribunal. (d) Place of Arbitration: The place of arbitration would be within the geographical limits of the Division of the Railway where the cause of action arose or the Headquarters of the concerned Railway or any other place with the written consent of both the parties, 64.(1) (iv) No new claim shall be added during proceedings by either party. However, a party may amend or supplement the original claim or defence thereof during the course of arbitration proceedings subject to acceptance by Tribunal having due regard to the delay in making it.
64.(1) (v) If the contractor(s) does/do not prefer his/their specific and final claims in writing, within a period of 90 days of receiving the intimation from the Railways that the final bill is ready for payment, he/they will be deemed to have waived his/their claim(s) and the Railway shall be discharged and released of all liabilities under the contract in respect of these claims."
4.
Since there are disputes between the parties, the petitioner invoked arbitration clause on 03.06.2024 and again on 03.09.2024. Thereafter, The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
the present petition is filed.
5.
Ms. Rai, learned counsel appears on behalf of the respondent and has no objection to the appointment of an Arbitrator. 6.
For the said reasons, I am satisfied that there are disputes pending between the parties which need to be adjudicated through the arbitral mechanism.
7.
For the said reasons, the petition is allowed and the following directions are issued:- i) Mr. Utkarsh (Advocate) (Mob. No. 9871926153) is appointed as a Sole Arbitrator to adjudicate the disputes between the parties.
ii) The arbitration will be held under the aegis and rules of the Delhi International Arbitration Centre, Delhi High Court, Sher Shah Road, New Delhi (hereinafter, referred to as the 'DIAC').
iii) The remuneration of the learned Arbitrator shall be in terms of DIAC (Administrative Cost and Arbitrators' Fees) Rules, 2018.
iv) The learned Arbitrator is requested to furnish a declaration in terms of Section 12 of the Act prior to entering into the reference.
v) It is made clear that all the rights and contentions of the parties, including as to the arbitrability of any of the claim, any other preliminary objection, as well as claims/counter-claims and merits of the dispute of either of the parties, are left open for adjudication by the learned arbitrator.
The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
vi) The parties shall approach the learned Arbitrator within two weeks from today.
8.
The present petition is disposed of in the aforesaid terms. JASMEET SINGH, J MAY 26, 2025/sp Click here to check corrigendum, if any The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.