IN THE HIGH COURT OF DELHI AT NEW DELHI

+ W.P.(C) 4507/2025 & CM APPL. 39591/2025 MAHENDER CHATURVEDI .....Petitioner Through:

Ms.

Chitrakshi, Advocate (M:9953358646) versus MUNICIPAL CORPORATION OF DELHI AND ANR.

.....Respondents Through:

Mr. Vikas Chopra, SC with Mr.

Neeraj Kumar and Ms.

Khushi, Advocates for MCD Mob: 9212036118 Email: chopra.company@gmail.com Mr. Sandeep Mandar and Mr. Amit Kumar, Advocates for R-3 Mob: 9811455642 Email: lawyer.mandar@gmail.com

CORAM:

HON'BLE MS. JUSTICE MINI PUSHKARNA

O R D E R

% 20.08.2025 1.

The present writ petition has been filed seeking demolition/sealing of the illegal and unauthorized construction being done by way of encroachment upon government land in property bearing no. J-3/92, J.J. Colony, Wazirpur, Delhi-110052.

2.

Today, learned counsel for the respondents-Municipal Corporation of Delhi ("MCD") submits that the area in question has more than 4000 plots, where more than 10,000 families are residing. 3.

He submits that a policy decision would have to be taken by the MCD, with regard to any action that would have to be taken in the area in The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 25/08/2025 at 12:15:52

question.

4.

Accordingly, in case so advised, the petitioner is granted liberty to file a Public Interest Litigation.

5.

Noting the aforesaid, the present writ petition, along with the pending application, is disposed of.

MINI PUSHKARNA, J AUGUST 20, 2025/au The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 25/08/2025 at 12:15:52