Chief Engineer National Highways Pwd Rajasthan Jaipur And ANR. v. M/S Mehta Construction Co.
$~67 *
IN THE HIGH COURT OF DELHI AT NEW DELHI
+ O.M.P. (COMM) 193/2023 GBK PROJECT PVT LTD ..... Petitioner Through:
Mr. SW Haider, Ms. Pooja Dua, Mr.
SV Abbas, Advs.
versus UNION OF INDIA ..... Respondent Through:
Mr. Jagdish Chandra, PSC with Mr.
Francis Fernandis, Mr. Hussain Taqvi, Advs.
CORAM:
HON'BLE MR. JUSTICE JASMEET SINGH
O R D E R
% 06.05.2024 I.A. 10019/2024-EX 1.
Exemption is granted subject to all just exceptions. 2.
The petitioner shall file legible and clearer copies of exempted documents, compliant with practice rules before the next date of hearing.
3.
The application is disposed of.
I.A. 10020/2024-DELAY IN RE-FILING 4.
This is an application seeking condonation of delay of 99 days in refiling the petition. 5.
Issue notice. Mr. Taqvi, learned counsel accepts notice on behalf of the respondent. He seeks and is granted 4 weeks to file a reply to this application.
6.
List on 12.08.2024.
The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 10/05/2024 at 11:46:27
O.M.P. (COMM) 193/2023 7.
Re-notify on 12.08.2024.
JASMEET SINGH, J MAY 6, 2024 / (MS) Click here to check corrigendum, if any The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 10/05/2024 at 11:46:27