Vinod Gupta v. Municipal Corporation Of Delhi & ANR.
$~62 *
IN THE HIGH COURT OF DELHI AT NEW DELHI
+ W.P.(C) 4550/2025 & CM APPL.
21049/2025, CM APPL.
21050/2025 VINOD GUPTA .....Petitioner Through:
Mr. Praveen Mahajan, Mr. Nakul, Mr.
Saura, Mr. Kunal Nema, Ms. Dipali Mittal, Advocates (M:9810620827) Email:advocatemahajan27@gmail.co m versus MUNICIPAL CORPORATION OF DELHI & ANR......Respondents Through:
Ms. Anshula L. Bakhru, Advocate for R-1/MCD Mr. Siddhanth Arora, Advocate for R2 (M:9839211111) Email:siddhantharora@live.com
CORAM:
HON'BLE MS. JUSTICE MINI PUSHKARNA
O R D E R
% 09.04.2025 1.
The present writ petition has been filed for directions to respondent no. 1-Municipal Corporation of Delhi ("MCD"), to stop and demolish the unauthorized construction being carried out in the property bearing no. 16A, Shri Ram Road, Civil Lines, Delhi.
2.
Learned counsel for respondent no. 1-MCD on advance notice, submits that construction being carried out in the property in question, is pursuant to the sanctioned Building Plan.
3.
Learned counsel for respondent no. 2, on advance notice, appearing for the owner/occupier of the building in question, has handed over a copy The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 15/04/2025 at 15:59:30
of the sanction granted by the MCD vide order dated 25th February, 2025. It is submitted that sanction Building Plan is valid till February, 2030. 4.
Thus, it is submitted that the construction of the building is being carried out after seeking relevant permission from the MCD and in accordance with the sanctioned Building Plan. 5.
Per contra, learned counsel for the petitioner submits that sanction for construction could not have been granted by the MCD, and that the same is against the norms, for the area in question.
6.
In case, the petitioner is aggrieved by the sanction of the building plan by the MCD, the petitioner is at liberty to seek appropriate legal remedies. 7.
Noting the aforesaid, the present petition, along with pending applications, is disposed of.
MINI PUSHKARNA, J APRIL 9, 2025 au The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 15/04/2025 at 15:59:30