High Court of DelhiO.M.P.(MISC.)(COMM.)/379/2026

Goyala Infra Projects Pvt Ltd v. The Engineer In Chief Military Engineering Services

2026-05-08Hon'Ble Mr. Justice Avneesh Jhingan1 pages

$~67 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P.(MISC.)(COMM.) 379/2026 & I.A. 12940/2026 GOYALA INFRA PROJECTS PVT LTD .....Petitioner Through:

Mr. Kushagra Bansal, Adv.

versus THE ENGINEER IN CHIEF MILITARY ENGINEERING SERVICES .....Respondent Through:

Mr. Niraj Kumar, Sr. Central Govt.

Counsel with Mr. Chaitanya Kumar, Advs.

CORAM:

HON'BLE MR. JUSTICE AVNEESH JHINGAN

O R D E R

% 08.05.2026 1.

This petition is filed under Section 29A of the Arbitration & Conciliation Act, 1996 seeking extension of period for concluding the arbitration proceedings.

2.

Learned counsel for the respondent has no serious objection to the prayer made.

3.

In view of the above, the time period for conclusion of the proceedings is extended by six months.

4.

This petition is disposed of in the aforesaid terms. AVNEESH JHINGAN, J MAY 8, 2026/Pa The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 12/05/2026 at 12:25:50