M/S Gpr Power Solutions Pvt. Ltd. v. General Motors India Pvt. Ltd.
$~38 *
IN THE HIGH COURT OF DELHI AT NEW DELHI
+ OMP (ENF.) (COMM.) 105/2021 and EX.APPL.(OS) 702704/2021, 834/2021, 1214-1217/2024 M/S GPR POWER SOLUTIONS PVT. LTD. .....Decree Holder Through:
Mr.
Sumit Kumar and Mr.
Nand Kishor Jha, Advocates versus GENERAL MOTORS INDIA PVT. LTD. ....Judgement Debtor Through:
Mr. Palzer Moktan, Advocate
CORAM:
HON'BLE MR. JUSTICE C.HARI SHANKAR
O R D E R
% 21.08.2024 1.
Learned counsel for the decree holder acknowledges that the entire awarded amount stands paid by the judgment debtor to the decree holder.
2.
The challenge to the award under execution filed by the respondent under Section 34 of the Arbitration and Conciliation Act, 1996 also stands dismissed.
3.
As such, learned counsel for both sides submit that this petition may be disposed of.
4.
As the award under execution stands satisfied, no further orders are required to be passed in the present petition, which is accordingly disposed of.
OMP (ENF.) (COMM.) 105/2021 The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 23/08/2024 at 11:17:51
5.
All pending applications also stand disposed of. C.HARI SHANKAR, J AUGUST 21, 2024/yg Click here to check corrigendum, if any OMP (ENF.) (COMM.) 105/2021 The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 23/08/2024 at 11:17:51