M/S Schenck Process Solutions India Private Limited v. Gail India Limited & ANR.
$~241 * IN THE HIGH COURT OF DELHI AT NEW DELHI + W.P.(C) 7921/2023, CM APPL. 30569/2023 & CM APPL. 30570/2023 M/S SCHENCK PROCESS SOLUTIONS INDIA PRIVATE LIMITED .....Petitioner Through:
Mr. Arvind Nayar, Senior Advocate with Mr. Praveen Arora, Mr. Prashant M.S., Mr. Aishwarya Kaushiq, Mr.
Lokesh Aidasani, Mr. Akshay Joshi, Ms. Sanjukta Kaushik, Mr. Parv Lodha and Mr. Anam Siddiqui, Advocates.
versus GAIL INDIA LIMITED & ANR.
.....Respondents Through:
Mr. Ajit Pudussery and Mr. Ashutosh Bamezai, Advocates for R-1.
Mr. Sandeep Kumar Mahapatra and Mr. Tribhuvan, Advocates for R-2.
CORAM:
HON'BLE THE CHIEF JUSTICE HON'BLE MR. JUSTICE TUSHAR RAO GEDELA
O R D E R
% 27.05.2025 1.
Learned counsel representing the respondent no.1 has stated that the work in relation to the tender, which is the subject matter of this writ petition, has already been completed. He hands over an inspection certificate wherein it is clearly observed that scope of supply has been completed. The said inspection certificate is taken on record. A copy of the inspection report has been furnished to the learned counsel for the petitioner as well. The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 01/07/2025 at 19:40:11
2.
In view of the aforesaid, nothing needs to be adjudicated any further in this petition, which is hereby disposed of as having been rendered infructuous.
3.
We may however, clarify that we have not adjudicated any issue raised in this writ petition on merits and as and when any such issue arises in any other matter, the same may be considered and decided in accordance with law.
DEVENDRA KUMAR UPADHYAYA, CJ TUSHAR RAO GEDELA, J MAY 27, 2025 yrj The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 01/07/2025 at 19:40:11