$~99 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P.(MISC.)(COMM.) 403/2026 & I.A. 14462/2026 ZAMIL STEEL BUILDINGS INDIA PVT. LTD. .....Petitioner Through:

Mr. Mrinal Beri, Adv.

versus CINDA ENGINEERING AND CONSTRUCTION PRIVATE LIMITED .....Respondent Through:

Ms. Pallavi Singh Rao, Ms. Sukanya Singh & Mr. Mainak Mukherjee, Advs.

CORAM:

HON'BLE MR. JUSTICE AVNEESH JHINGAN

O R D E R

% 22.05.2026 1.

This petition is filed under Section 29A of the Arbitration & Conciliation Act, 1996 seeking extension of period for concluding the arbitration proceedings.

2.

Learned counsel for the respondent has no serious objection to the prayer made.

3.

In view of the above, the time period for conclusion of the proceedings is extended by six months as prayed for. 4.

This petition is disposed of in the aforesaid terms. Pending application stands disposed of.

AVNEESH JHINGAN, J MAY 22, 2026 'ha'