Zebboi Facility Developers Private Limited & ANR. v. All India Football Association & ORS.
$~31 * IN THE HIGH COURT OF DELHI AT NEW DELHI + W.P.(C) 8035/2026, CM APPL. 38492/2026-Interim orders. ZEBBOI FACILITY DEVELOPERS PRIVATE LIMITED & ANR.
.....Petitioners Through:
Mr. Sanjoy Ghose, Sr. Adv. with Mr. Yashit Jain and Ms. Ishita Agarwal, Advs.
versus ALL INDIA FOOTBALL ASSOCIATION & ORS......Respondents Through:
Mr. Arjun Mukherjee and Ms.
Komal Kinger, advs. for R-2 Mr.
Siddhartha Shankar Ray, CGSC with Ms. Sonali Modi and Mr. Mukul Dev, Advs. for R-3
CORAM:
HON'BLE MR. JUSTICE SAURABH BANERJEE
O R D E R
% 03.06.2026 1.
By virtue of the present petition under Article 226 of the Constitution of India, the petitioners seek following reliefs:- "I.
Issue Writ of Mandamus or any other Writ of the appropriate nature or order or direction quashing the letter dated 23.05.2026 issued by All India Football Federation and email dated 23.05.2026 issued by Delhi Soccer Association cancelling the Extraordinary General Meeting of DSA to be held on 24.05.2026.
AND II.
Pass an ad-interim ex-parte order in terms of the separately contained application for interim directions AND/OR III.
Pass such other and further order(s) that this Hon'ble Court deems fit and proper in the facts and circumstances of the present case and in the interest of justice/equity." 2.
At the outset, learned senior counsel for the petitioners has handed over a copy of the letter dated 28.05.2026 issued by the Delhi Soccer The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 05/06/2026 at 11:22:37
Association/ respondent no.2 which is taken on record. 3.
Considering the same, learned senior counsel for the petitioners submits that it would be in the interest of justice of all the parties involved herein if, in view thereof, the petitioners are granted a period of one week for making a composite representation dealing with the letter dated 23.05.2026 issued by the respondent no.1/ AIFA as well as the e-mail dated 23.05.2026 issued by the respondent no.2 alongwith the letter dated 28.05.2026 issued by respondent no.2/ DSA.
4.
Learned counsel for the respondent no.2/ DSA submits that he does not have any objection to the same. He in fact submits that the same shall be adverted to, and disposed of, after giving a hearing to the petitioners within a period of four weeks thereafter, a copy whereof shall be communicated to the petitioners within a period of three days thereafter so that the same be taken up in the extraordinary General Body (EGM) of the respondent no.2/ DSA to be convened on 19.07.2026. 5.
Needless to mention, in view thereof, the respondent no.2/ DSA shall write to the AIFF who, by virtue of order dated 03.04.2026 requested it "... ...to complete adoption of amendments to their constitutional document on or before 30.06.2026... ...".
6.
In view thereof, since there is nothing remaining in the present petition, the same is disposed of in the aforesaid terms. SAURABH BANERJEE, J.
(VACATION JUDGE) JUNE 03, 2026/rr The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 05/06/2026 at 11:22:37