$~31 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P. (MISC.) 17/2024 M/S AJIT CONSTRUCTION COMPANY ..... Petitioner Through:

Mr. G. L. N. Murthy, Adv.

versus STATE OF HARYANA PWD B AND R & ANR. ..... Respondents Through:

Mr. Krishnan Kumar, Mr. Seemant K Garg, Mr. Nitin Pal, Advs.for R-2

CORAM:

HON'BLE MR. JUSTICE DINESH KUMAR SHARMA

O R D E R

% 07.05.2024 I.A. 10385/2024 (exemption) Exemption is allowed subject to all just exceptions O.M.P. (MISC.) 17/2024

1. Present petition has been filed under Section 29-A of the Arbitration and Conciliation (amendment) Act, 2021 for extension of mandate for a period of four months for enabling the learned Tribunal to pass award in dispute.

2. Issue notice.

3. Mr. Krishnan Kumar, learned counsel for the respondents accepts the notice and submits that the final arguments have already been concluded and learned Arbitrator has to pronounce the award. Learned counsel submits that appropriate order may be passed. It is submitted that the mandate expired on 01.03.2024 and may be The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 13/05/2024 at 11:23:10

extended till 31.07.2024.

4. In view of the above, the mandate is extended till 31.07.2024.

5. The period from 01.03.2024 till now is also regularized.

6. In view of the above, the present petition stands disposed of. DINESH KUMAR SHARMA, J MAY 7, 2024 Pallavi The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 13/05/2024 at 11:23:10