Well Protect Manpower Services Pvt. Ltd v. Meera Bai Institute Of Technology
$~15 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P.(MISC.)(COMM.) 455/2026 & I.A. 16214/2026 WELL PROTECT MANPOWER SERVICES PVT. LTD .....Petitioner Through:
Mr. Tarkeshwar Nath, Mr. Harshit Singh and Mr. Anant, Advs.
versus MEERA BAI INSTITUTE OF TECHNOLOGY .....Respondent Through:
Ms. Avni Singh, Adv and Mr.
Abhinav Singh, Advs.
CORAM:
HON'BLE MR. JUSTICE AVNEESH JHINGAN
O R D E R
% 01.07.2026 1.
This petition is filed under Section 29A of the Arbitration & Conciliation Act, 1996 seeking extension of period for concluding the arbitration proceedings.
2.
Learned counsel for the parties submits that the amount involved is less than two crores.
3.
The original jurisdiction is not with this court. The application has to be made before the commercial court concerned. Reference in this regard be made to the decision of the Supreme Court in Jagdeep Chowgule v. Sheela Chowgule & Ors. 2026 INSC 92.
4.
The petition is disposed of with liberty to approach the commercial court concerned.
AVNEESH JHINGAN, J JULY 1, 2026/Pa The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 03/07/2026 at 11:41:48