$~A-9 * IN THE HIGH COURT OF DELHI AT NEW DELHI + C.R.P. 193/2023 & CM APPL. 37107/2023 H DOHIL CONSTRUCTION CO. PRIVATE LIMITED .....Petitioner Through:

Appearance not given.

versus HINDUSTAN ZINC LIMITED .....Respondent Through:

Mr. Pallav Mongia and Mr. Anubhav Mishra, Advocates.

CORAM:

HON'BLE MR. JUSTICE CHANDRA DHARI SINGH

O R D E R

% 02.08.2024 Learned counsel appearing on behalf of the petitioner seeks leave to withdraw the instant petition with liberty to file a fresh applicaiton in accordance with law.

Leave granted.

Accordingly, the instant petition along with pending application(s) is dismissed as withdrawn with liberty as prayed for. CHANDRA DHARI SINGH, J AUGUST 2, 2024 Rk/aa Click here to check corrigendum, if any The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 02/07/2025 at 14:01:32