High Court of DelhiOMP (ENF.) (COMM.)/109/2024

Rishabh Constructions Pvt. Ltd. v. Union Of India

2024-07-02Hon'Ble Mr. Justice Jasmeet Singh2 pages

$~42 *

IN THE HIGH COURT OF DELHI AT NEW DELHI

+ OMP (ENF.) (COMM.) 109/2024 RISHABH CONSTRUCTIONS PVT. LTD.

.....Decree Holder Through:

Mr. Dinesh Kumar Mishra, Adv.

Versus

UNION OF INDIA .....Judgement Debtor Through:

Mr. RP Singh, Mr. Anand J Vijay, Advs.

CORAM:

HON'BLE MR. JUSTICE JASMEET SINGH

O R D E R

% 21.10.2024 EX.APPL.(OS) 1147/2024 1.

This is an application seeking recall of the order dated 02.07.2024 passed in O.M.P. (ENF.)(COMM.) 109/2024.

2.

Mr. Singh, learned counsel for the judgment-debtor seeks to withdraw the application.

3.

The application is dismissed as withdrawn.

OMP (ENF.) (COMM.) 109/2024 & EX. APPL. (OS) 1148/2024 4.

This is a petition seeking enforcement of the interim award dated 07.01.2024, wherein the learned Sole Arbitrator had directed release of three bank guarantees of the decree holder. The details of the bank guarantees are as under:- The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 25/10/2024 at 14:28:57

S. No.

Bank Guarantee Amount of Date of Bond No.

BGB (Rs.) Issuance of BG 1.

18901GPER002015 1,40,00,000/- 12.03.2015 2.

18901GPER004615 70,00,000/- 19.09.2015 3.

18901GPER003714 8,81,19,000/- 03.03.2014 5.

It is stated that the bank guarantees as directed in the interim award dated 07.01.2024 passed by the sole arbitrator has been released in favour of the decree-holder.

6.

For the said reasons, the interim Award dated 07.01.2024 stands satisfied and the present petition is disposed of. JASMEET SINGH, J OCTOBER 21, 2024/NG The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 25/10/2024 at 14:28:57