Gaurav Enterprises v. Guru Teg Bahadur Hospital & ANR
$~ * IN THE HIGH COURT OF DELHI AT NEW DELHI + W.P.(C) 1276/2014 & CM APPLs. 2631/2014, 15802/2015 AND 29719/2015 GAURAV ENTERPRISES ..... Petitioner Through: Mr. Tarkeshwar Nath, Advocate with Mr. Saurabh Kumar Tuteja, Advocate.
versus GURU TEG BAHADUR HOSPITAL & ANR ..... Respondents Through: Mr. Naushad Ahmed Khan, Advocate for respondents No.1 and 2 with Mr. P.R. Yadav, Legal Assistant, GTB Hospital.
CORAM:
HON'BLE MR. JUSTICE MANMOHAN
O R D E R
% 28.01.2016 Present writ petition has been filed with the following prayers:- " (i) Quash and set aside the letter dated 30.07.2013 issued by the respondent.
(ii) Direct the respondent to allow the petitioner to work in terms of final letter of award dated 19.07.2013. (iii) Pass any other order that is deemed fit and proper under the facts and circumstances of the case."
By the final Award dated 19th July, 2013, the petitioner had been awarded contract for providing Watch and Ward/Door Keeping Services in
GTB Hospital for a period of two years w.e.f. 01st August, 2013. Admittedly, the period of the said contract has expired on 01st August, 2015.
Consequently, in the opinion of this Court, present writ petition and application are infructuous and they accordingly stand disposed of. Petitioner's bank guarantee is directed to be released within a period of two weeks.
However, the petitioner is given liberty to file a claim for damages, if so available, in accordance with law.
MANMOHAN, J JANUARY 28, 2016 js