Ms Bridge Building Construction Co Pvt Ltd v. Bharat Heavy Electricals Ltd
$~O-1 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P.(MISC.)(COMM.) 265/2020 MS BRIDGE BUILDING CONSTRUCTION CO PVT LTD ..... Petitioner Through Mr.Sanjay Kumar Shandilya, Adv.
versus BHARAT HEAVY ELECTRICALS LTD ..... Respondent Through Mr.Pallav Kumar, Adv.
CORAM:
HON'BLE MR. JUSTICE C.HARI SHANKAR O R D E R (O R A L) % 23.11.2020 (Video-Conferencing) I.A. No.10824/2020 (Exemption) 1.
Exemption allowed, subject to all just exceptions. 2.
The applications stand disposed of.
O.M.P.(MISC.)(COMM.) No.265/2020 1.
This petition seeks extension of the time available with the learned sole Arbitrator to conclude the arbitral proceedings and pass award.
2.
Mr.Pallav Kumar, learned counsel appearing for the respondent, has no objection.
SINGH NEGI OMP (MISC.) (COMM.) 265/2020 16:34:57
3.
Accordingly, the time available with the learned sole Arbitrator, to complete arbitral proceedings and render award, is extended by a period of nine months from today.
4.
The petition is allowed in the aforesaid terms. C.HARI SHANKAR, J NOVEMBER 23, 2020/aa SINGH NEGI OMP (MISC.) (COMM.) 265/2020 16:34:57