High Court of DelhiO.M.P.(MISC.)(COMM.)/407/2025

M/S Allied Engineers Through Its Authorized Partner v. Hindustan Prefab Limited Through Its Chief Managing Director

2025-05-22Hon'Ble Ms. Justice Manmeet Pritam Singh Arora2 pages

$~89 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P.(MISC.)(COMM.) 407/2025 M/S ALLIED ENGINEERS THROUGH ITS AUTHORIZED PARTNER .....Petitioner Through:

Mr. Avinash Trivedi and Mr. Rahul Aggarwal, Advocates versus HINDUSTAN PREFAB LIMITED THROUGH ITS CHIEF MANAGING DIRECTOR .....Respondent Through:

Mr. Varun Nischal, Advocate

CORAM:

HON'BLE MS. JUSTICE MANMEET PRITAM SINGH ARORA

O R D E R

% 22.05.2025 1.

This is a petition filed under Section 29A(4) of the Arbitration and Conciliation Act, 1996 seeking extension of the mandate of the Arbitral Tribunal.

2.

Issue notice. Mr. Varun Nischal, Advocate for Respondent accepts notice.

3.

It is stated in the petition that the mandate of the arbitral tribunal expired on 16.11.2024.

4.

It is stated that pleadings in the claim filed by the Petitioner and the counter claim filed by the Respondent have been completed. It is stated that evidence in the claims is being led presently and are still pending completion.

5.

It is stated that parties reasonably expect to complete the arbitral O.M.P.(MISC.)(COMM.) 407/2025 The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 01/07/2025 at 16:31:10

proceedings within a period of one (1) year from today. 6.

It is prayed that the period between 16.11.2024 until today be regularized and a further period of one year be granted for completion of the arbitral proceedings.

7.

Learned counsel for the Respondent states that he has no objection to the relief sought in this petition; he, however, does not admit to the allegations made on the merits of the dispute in the petition. 8.

This Court has heard the parties.

9.

In view of the submissions recorded hereinabove, the mandate of the arbitral tribunal is extended till 31.05.2026. The period between 16.11.2024 until 21.05.2025 is hereby regularized.

10.

The parties are directed to cooperate with the arbitral tribunal in expeditious recording of evidence and arguments, so that the mandate of the arbitration of an early disposal is meaningfully achieved. Parties undertake not to seek any unnecessary adjournment. The learned sole Arbitrator is requested to complete the arbitration proceedings within the extended period.

11.

With the aforesaid directions, the present petition stands disposed of. MANMEET PRITAM SINGH ARORA, J MAY 22, 2025/rhc/MG Click here to check corrigendum, if any O.M.P.(MISC.)(COMM.) 407/2025 The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 01/07/2025 at 16:31:10