$~435, 436, 454 * IN THE HIGH COURT OF DELHI AT NEW DELHI + W.P.(C) 6899/2025 RAM NARAYAN .....Petitioner Through:

Mr. Ashok Agarwal, Mr. Kumar Utkarsh, Mr. Manoj Kumar, Ms.

Ashna Khan, Advocates versus THE COLLECTOR/ DISTRICT MAGISTRATE & ORS.

.....Respondents Through:

Mr.Raghvendra Upadhyay, Panel Counsel with Mr.Chandra Kishore Yadav & Ms.Pratibha Jain, Advocates for GNCTD + W.P.(C) 7086/2025 RAJENDER SINGH ALIAS RAJU & ORS.

.....Petitioner Through:

Mr. Anjali Bansal and Ms. Kritika Matta, Advocates.

versus THE DISTRICT MAGISTRATE & ORS.

.....Respondents Through:

Counsel for respondents.

+ W.P.(C) 16171/2024 MUKESH KUMARI .....Petitioner Through:

Mr. R.K. Nain, Advocate.

versus SUB DIVISIONAL MAGISTRATE, NAJAFGARH (DISTRICT - SOUTH WEST) & ORS.

.....Respondents Through:

Mr. Anubhav Gupta, Advocate for GNCTD.

CORAM:

HON'BLE MR. JUSTICE MANOJ KUMAR OHRI

O R D E R

% 28.05.2025 1.

By way of present batch of petitions, the petitioners seek implementation of the recovery certificates that were issued in the context of The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 01/07/2025 at 20:27:15

respective awards/orders passed under various statues in favour of the petitioners.

2.

It is the common grievance of the petitioners that despite the awards/orders having attained finality and the recovery certificate having been issued, the same remain to be implemented for the lethargy of the concerned SDMs. In this regard, it is informed that the Labour Department, GNCTD has already come out with a notification dated 05.07.2019 which provides the guidelines not only for the issuance of recovery certificates but also for its implementation. It is further stated that despite the same, the concerned SDMs have not carried out the requisite steps in a time-bound manner.

3.

Learned counsel appearing for GNCTD assures the Court that the implementation of recovery certificate would be carried out within a period of four weeks and the guidelines in the notification would be adhered to in future as well. The statement made on behalf of State Government is taken on record. In lieu thereof, the cost imposed, if any, is waived. 4.

The petitions are disposed of in the aforesaid terms. MANOJ KUMAR OHRI, J MAY 28, 2025/rd The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 01/07/2025 at 20:27:15