← Library
High Court of DelhiO.M.P. (COMM)/609/2020

Union Of India v. Mfar Constructions Pvt. Ltd

2024-08-22Hon'Ble Mr. Justice Prateek Jalan2 pages

$~19 & 20 *

IN THE HIGH COURT OF DELHI AT NEW DELHI

+ O.M.P. (COMM) 609/2020, I.A. 12717/2020, I.A. 12718/2020 & I.A. 37064/2024 UNION OF INDIA .....Petitioner Through:

Ms. Nidhi Raman, CGSC with Mr.

Zubin Singh and Ms.

Rashi Kapoor, Advocates.

versus MFAR CONSTRUCTIONS PVT. LTD .....Respondent Through:

Mr. Bhardwaj S. Iyengar and Mr.

Vikram, Advocates.

+ O.M.P. (COMM) 51/2021 & I.A. 37073-74/2024 MFAR CONSTRUCTIONS PRIVATE LIMITED .....Petitioner Through:

Mr. Bhardwaj S. Iyengar and Mr.

Vikram, Advocates.

versus UNION OF INDIA .....Respondent Through:

Mr. Rajesh Gogna, CGSC with Mr.

Nipun Jain and Ms. Priya Singh, Advocates.

CORAM:

HON'BLE MR. JUSTICE PRATEEK JALAN

O R D E R

% 22.08.2024 1.

These are cross petitions, under Section 34 of the Arbitration and Conciliation Act, 1996 ["the Act"], assailing an arbitral award dated O.M.P. (COMM) 609/2020 & O.M.P. (COMM) 51/2021 The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 27/08/2024 at 11:43:50

25.09.2020.

2.

The parties have since settled their disputes. Both the parties have filed applications for withdrawal of the petitions [I.A. 37064/2024 in O.M.P. (COMM) 609/2020 and I.A. 37073/2024 in O.M.P. (COMM) 51/2021] 3.

Learned counsel for the parties are present and confirm the settlement.

4.

The applications are, therefore, allowed and O.M.P. (COMM) 609/2020 and O.M.P.

(COMM) 51/2021, alongwith all pending applications, are dismissed as withdrawn.