Ssangyong Engineering & Construction Co. Ltd. v. National Highways Authority Of India (Nhai)
$~17 * IN THE HIGH COURT OF DELHI AT NEW DELHI + OMP (ENF.) (COMM.) 148/2019, EX. APPL.(OS) 479/2019 SSANGYONG ENGINEERING & CONSTRUCTION CO. LTD. ..... Decree Holder Through:
Mr. Navin Kumar, Ms. Rashmeet Kaur and Ms. Arpana Majumdar, Advs.
versus NATIONAL HIGHWAYS AUTHORITY OF INDIA (NHAI) ..... Judgement Debtor Through:
Mr. Ankur Chhibber and Mr. Bhanu Gupta, Advs.
CORAM:
HON'BLE MR. JUSTICE V. KAMESWAR RAO
O R D E R
% 09.01.2020 This is a petition filed by the petitioner seeking enforcement of an interim award dated May 18, 2019. Learned counsel for the Judgment Debtor states that he has instructions that the payment in terms of the interim award shall be paid to the petitioner within four weeks from today. Noting the said submission, the petition and connected application are disposed of giving liberty to the petitioner, in the eventuality the statement made by the learned counsel for the Judgment Debtor is not complied with, the petitioner can revive the present petition. The petition and connected application are disposed of. V. KAMESWAR RAO, J JANUARY 09, 2020/aky