$~O-24 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P.(MISC.)(COMM.) 449/2025 NCC LTD.
.....Petitioner Through:
Mr.Adhish Srivastava, Advocate.
versus YUVAL INFRATECH PVT. LTD.
.....Respondent Through:
Mr.Nitesh Mehra, Ms.Hitakshi, Ms.Neshu, Ms.Sabreena, Ms.Vanshika and Ms.Parmika, Advocates.
CORAM:
HON'BLE MR. JUSTICE PURUSHAINDRA KUMAR KAURAV
O R D E R
% 30.05.2025 1.
The petitioner, in the instant petition prays for the following relief:- "a. Allow the present Petition and grant an extension to the Arbitral Tribunal comprising of Mrs. Kanwal rnder (Retd. District Judge), an extension of six months for making the Award i.e. from 01.04.2025 to 01.10.2025."
2.
With the consent of the parties, the instant petition stands allowed in terms of prayer Clause (a).
3.
Ordered accordingly.
4.
In view thereof, the instant petition stands disposed of. PURUSHAINDRA KUMAR KAURAV, J MAY 30, 2025 Nc/sph Click here to check corrigendum, if any The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 01/07/2025 at 16:31:25