$~31 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P.(MISC.)(COMM.) 364/2019, I.A. 12543/2019 RAJSHEKHAR CONSTRUCTION PVT.LTD.

..... Petitioner Through:

Mr. Sujatha Balachander, Ms.

Shreyek Gupta, Ms. Malvika Tiwari, Mr. Poojan Kapoor, Ms. Shikha Mehndiratta and Mr. Rajat Bhatia, Advs.

versus BRAHMAPUTRA CRACKERS & POLYMERS LTD.

..... Respondent Through:

Mr. Yasir Rauf, Adv.

CORAM:

HON'BLE MR. JUSTICE V. KAMESWAR RAO

O R D E R

% 11.09.2019 I.A. 12543/2019 (for exemption) Exemption allowed subject to all just exceptions. Application stands disposed of.

O.M.P.(MISC.)(COMM.) 364/2019 This is a petition under Section 29A(5) of the Arbitration and Conciliation Act, 1996 seeking extension of six months for the Arbitral Tribunal to complete the proceedings and render the arbitral award. Noting the contents of the petition and the learned counsel for the respondent has consented to the same; the time for Arbitral Tribunal to complete the proceedings and render the arbitral award is extended by a period of six months effective from the second week of September 2019. The petition stands disposed of.

V. KAMESWAR RAO, J SEPTEMBER 11, 2019/aky