← Library
High Court of DelhiW.P.(C)/8467/2025

Mrs Archana Aggarwal v. Delhi Jal Board & ORS.

2025-07-03Hon'Ble Ms. Justice Mini Pushkarna2 pages

$~25 *

IN THE HIGH COURT OF DELHI AT NEW DELHI

+ W.P.(C) 8467/2025 & CM APPL.

42941/2025, CM APPL.

61585/2025, CM APPL. 62617/2025 MRS ARCHANA AGGARWAL .....Petitioner Through:

Mr.

Abhishek Parmar, Mr.

Atul Parmar and Ms. Kirti Parmar, Advs.

M: 9643852438 Mob: 9643852438 versus DELHI JAL BOARD & ORS.

.....Respondents Through:

Mr. Manish Srivastava, Mr. Moksh Arora and Mr. Santosh Ramdurg, Advs. for BSES M: 7982486879 Ms. Sangeeta Bharti, SC with Ms.

Malvi Balyan, Adv. for DJB M: 9811112863 Ms. Meghna Bali, Advocate for R-4 Mob: 9968826489 Email: baliandbali.legal@gmail.com Mr. Satya Ranjan Swain, CGSC with Mr.

Kautilya Birat, Mr.

Ankush Kapoor and Mr.

Vishwadeep, Advocates for R-2. (through VC) Email -thechambers.srs@gmail.com Mob: 8869189238

CORAM:

HON'BLE MS. JUSTICE MINI PUSHKARNA

O R D E R

% 11.12.2025 The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 15/12/2025 at 13:08:52

CM APPL. 42941/2025 1.

The present application has been filed on behalf of the petitioner for modification/clarification of the order dated 03rd July, 2025, passed in the present writ petition.

2.

Learned counsel appearing for the petitioner submits that in the said order, it has been stated that the electricity meter and the water motor meter were in the basement of the property bearing No. C-21, Ground Floor, Ganesh Nagar, Shakarpur, Delhi-110092. However, it is submitted that the electricity meter was installed in the premises of the petitioner on the Ground Floor, and not in the basement of the property. 3.

The aforesaid statement is taken note of.

4.

Noting the aforesaid, the present application is disposed of. CM APPL. 61585/2025 & CM APPL. 62617/2025 5.

This Court is informed that pursuant to the directions issued vide order dated 06th October, 2025, the electricity meter already stands shifted. 6.

Thus, no further orders are required to be passed in the present writ petition.

7.

The present applications are accordingly disposed of. MINI PUSHKARNA, J DECEMBER 11, 2025 ak The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 15/12/2025 at 13:08:52