← Library
High Court of DelhiO.M.P.(MISC.)(COMM.)/395/2019

Concept Horizon Infra Private Limited v. Suninder Sandha, & ORS.

2019-10-15Hon'Ble Mr. Justice V. Kameswar Rao1 pages

$~30 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P.(MISC.)(COMM.) 395/2019 CONCEPT HORIZON INFRA PRIVATE LIMITED ..... Petitioner Through:

Mr. Vikrant Singh Bloria and Mr. Samith, Advs.

versus SUNINDER SANDHA, & ORS.

..... Respondents Through:

Mr. Adhirath Singh and Mr. Ashish Garg, Advs.

CORAM:

HON'BLE MR. JUSTICE V. KAMESWAR RAO

O R D E R

% 15.10.2019 This petition has been filed by the petitioner under Section 29A (5) of the Arbitration and Conciliation Act, 1996 for extension of time for the sole Arbitrator to complete the arbitral proceedings and render the award. Noting the contents of the petition, more specifically, the averments made in Para 10 and the learned counsel for the respondents has given his consent, the period for the learned Arbitrator to complete the proceedings and render the award is extended by a period of one year from today. The petition stands disposed of.

V. KAMESWAR RAO, J OCTOBER 15, 2019/jg