High Court of DelhiW.P.(C)/9751/2025

Sh Shakti Singh v. Municipal Corporation Of Delhi & ANR.

2025-09-23Hon'Ble Ms. Justice Mini Pushkarna6 pages

$~62 * IN THE HIGH COURT OF DELHI AT NEW DELHI + W.P.(C) 9751/2025 SH SHAKTI SINGH .....Petitioner Through:

Mr. Bharat Sareen, Advocate (through VC) versus MUNICIPAL CORPORATION OF DELHI & ANR. .....Respondents Through:

Ms. Manisha, Mr. Shubhashish and Mr. Arjun Gupta, Advocates for R-2 Mob: 9667440544 Emai: adv.manishatnwr@gmail.com Mr. Rakesh Malhotra and Mr. Bharat Malhotra, Advs. for MCD Mob: 8447151507 Email: bharatmal2@gmail.com

CORAM:

HON'BLE MS. JUSTICE MINI PUSHKARNA

O R D E R

% 23.09.2025 1.

The present writ petition has been filed seeking directions to the respondent no. 1, to demolish the illegal construction at the property bearing Khasra No. 30, Bhati Village, Chattarpur, New Delhi-110074. 2.

A Status Report dated 20th September, 2025, has been filed on behalf of the Municipal Corporation of Delhi ("MCD"), relevant portions of which, read as under:

The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.

The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.

The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.

The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.

3.

Perusal of the aforesaid Status Report shows that the MCD had issued the Demolition Order with respect to the property in question. Further, partial demolition action was taken on 12th August, 2025. Additionally, a Letter dated 27th August, 2025 has also been issued to the Station House Officer ("SHO"), Police Station - Fatehpur Beri, to keep a strict watch and ward over the subject property.

4.

It is further submitted by the MCD in its Status Report that further action programme with respect to the subject property is fixed for 29th September, 2025.

5.

Accordingly, no further orders are required to be passed in the present petition.

6.

Learned counsel appearing for respondent no. 2 submits that respondent no. 2 has not received any Demolition Order. 7.

The respondent no. 2 is granted liberty to seek his remedies, in accordance with law.

8.

It is clarified that this Court has not expressed any opinion with The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.

respect to the title of the property in question. 9.

With the aforesaid directions, the present writ petition is accordingly disposed of.

MINI PUSHKARNA, J SEPTEMBER 23, 2025 ak The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.