High Court of DelhiO.M.P.(MISC.)(COMM.)/536/2025

Puja Sharma v. M/S Gtl Infrastructure Ltd. ORS.

2025-07-15Hon'Ble Mr. Justice Jasmeet Singh1 pages

$~75 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P.(MISC.)(COMM.) 536/2025 & I.A. 16421/2025 PUJA SHARMA .....Petitioner Through:

versus M/S GTL INFRASTRUCTURE LTD. ORS.

.....Respondent Through:

Mr. Ankit Kumar & Mr. Shreyansh Anand, Advs.

CORAM:

HON'BLE MR. JUSTICE JASMEET SINGH

O R D E R

% 15.07.2025 1.

This is a petition filed under Section 29A(4) & (5) of the Arbitration and Conciliation Act, 1996 seeking extension of the mandate of the Arbitral Tribunal by a period of 6 months.

2.

It is stated that the matter is at the stage of final arguments and hence, the delay.

3.

For the said reasons, issue notice.

4.

Mr. Kumar, learned counsel accepts notice on behalf of the respondent and has no objection to the petition being allowed. 5.

For the reasons noted above, I am of the view that sufficient cause has been explained for the delay. The petition is allowed and the mandate of the Arbitral Tribunal is extended by a period of 6 months from today to make and publish the Award.

6.

The period from 24.09.2024 till today stands regularised. 7.

The petition is disposed of.

JASMEET SINGH, J JULY 15, 2025/sp The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 22/07/2025 at 12:22:25