Krishna Devi & ORS. v. The State Of Gnct Of Delhi & ANR.
$~28 * IN THE HIGH COURT OF DELHI AT NEW DELHI + CRL.M.C. 5251/2025 KRISHNA DEVI & ORS.
.....Petitioners Through:
Ms. Jyoti Verma and Mr. Radhe Sham Rohilla, Advs.
versus THE STATE OF GNCT OF DELHI & ANR.
.....Respondents Through:
Mr. Shoaib Haider, APP for the State with SI Ayushi Raj and Respondent No.2 in person.
CORAM:
HON'BLE MS. JUSTICE NEENA BANSAL KRISHNA
O R D E R
% 19.11.2025 1.
Petition under Section 528 of the Bhartiya Nagrik Suraksha Sanhita, 2023 has been filed on behalf of the Petitioners for quashing of FIR No.0289/2018 under Sections 498A/406 IPC registered at PS: Bawana, Delhi, in terms of Joint Settlements dated 07.01.2019 and 31.01.2019 2.
Respondent No.2 is present in person and she submits that certain amount of agreed Rs.2,25,000/- has not been paid till date. 3.
Learned counsel for the Petitioner points out various payments, which are only coming to Rs.1,60,000/-. It is submitted that Rs.25,000/- was paid at the time of withdrawal of DV Act Petition, though there is no documentary proof to this effect.
4.
But, even though, if it is accepted that Rs.25,000/- was also paid, then too it becomes Rs.1,85,000/-, which is less than Rs.2,25,000/- and balance amount is remaining, as has been submitted by Respondent No.2. 5.
In view of aforesaid, it is evident that all terms of the settlements have The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 22/11/2025 at 12:19:16
not been complied with by the Petitioners.
6.
Petition along with pending Application is disposed of with liberty to the Petitioner to file afresh after complying with the terms of settlements. NEENA BANSAL KRISHNA, J.
NOVEMBER 19, 2025/R The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 22/11/2025 at 12:19:16