High Court of DelhiO.M.P. (COMM)/374/2024

Chief Engineer National Highway Public Works Department Government Of Uttar Pradesh v. Dra S And P Joint Venture

2024-09-18Hon'Ble Mr. Justice C.Hari Shankar1 pages

$~47 *

IN THE HIGH COURT OF DELHI AT NEW DELHI

+ O.M.P. (COMM) 374/2024, I.A. 38151/2024, I.A. 38152/2024, I.A. 38153/2024 & I.A. 38154/2024 CHIEF ENGINEER NATIONAL HIGHWAY PUBLIC WORKS DEPARTMENT GOVERNMENT OF UTTAR PRADESH .....Petitioner Through:

Ms. Rashmi Singh, Adv.

versus DRA S AND P JOINT VENTURE .....Respondent Through:

CORAM:

HON'BLE MR. JUSTICE C.HARI SHANKAR

O R D E R

% 18.09.2024 1.

Ms. Rashmi Singh, learned Counsel for the petitioner very fairly states, at the very outset, that this petition has been filed beyond 37 days, beyond 3 months and 30 days from the date of receipt of the impugned arbitral award.

2.

It is clear that the Court cannot condone the delay beyond 3 months and 30 days from the receipt of the arbitral award. 3.

Accordingly, this petition is dismissed on the ground of delay. C.HARI SHANKAR, J SEPTEMBER 18, 2024/aky Click here to check corrigendum, if any The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 03/07/2025 at 02:46:21