Sushil Pandey v. Green Bay Infrastructure Pvt Ltd Through Its Director & ANR.
$~17 * IN THE HIGH COURT OF DELHI AT NEW DELHI + CS(COMM) 779/2024 & I.A. 39080/2024, I.A. 39081/2024, I.A. 39082/2024, I.A. 39083/2024 SUSHIL PANDEY .....Plaintiff Through:
Mr.Varun Varma, Mr.Prakhar Shukla, Advs.
versus GREEN BAY INFRASTRUCTURE PVT. LTD THROUGH ITS DIRECTOR & ANR.
.....Defendants Through:
None.
CORAM:
HON'BLE MR. JUSTICE NAVIN CHAWLA
O R D E R
% 11.09.2024 1.
The learned counsel for the plaintiff prays for leave to withdraw the present suit with liberty to file afresh before a Court of competent jurisdiction.
2.
The suit is accordingly, dismissed as withdrawn with liberty as prayed for.
3.
As the plaintiff has withdrawn the suit before summons could be issued to the defendants, the plaintiff is entitled to refund of the court fee deposited with the plaint.
4.
The Registry is directed to prepare a certificate of refund in favour of the plaintiff and hand it over to the learned counsel for the plaintiff.
5.
The pending applications are disposed of as having become infructuous.
NAVIN CHAWLA, J SEPTEMBER 11, 2024 RN/as The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 02/07/2025 at 15:40:11