North Delhi Metro Mall Private Limited v. Tpc Technical Project Cosultants Private Limited
$~15 *
IN THE HIGH COURT OF DELHI AT NEW DELHI
+ O.M.P. (E) (COMM.) 31/2025 NORTH DELHI METRO MALL PRIVATE LIMITED .....Petitioner Through:
Mr. Kamal Shankar, Ms. Swati Sharma & Mr. Mukund Rawat, Advs.
versus TPC TECHNICAL PROJECT COSULTANTS PRIVATE LIMITED .....Respondent Through:
Mr.
Sanjay Gupta & Mr.
Shawaiz Nisar, Advs.
CORAM:
JOINT REGISTRAR (JUDICIAL) MS. PREETI PAREWA, (DHJS)
O R D E R
% 28.08.2025 O.M.P. (E) (COMM.) 31/2025 Learned counsel for the respondent present accepts notice of the captioned petition and submits that he has no objection to the same.
In view of above and in view of reasons mentioned in captioned petition, the captioned petition stands allowed and let the witnesses mentioned in the prayer clause of the captioned petition be summoned through all permissible modes before the learned Arbitrator with complete summoned records, if any, on taking steps by the applicant/petitioner within two weeks from today. It is clarified that the diet money to the witness/es shall be borne by the petitioner and be payable at the spot. Accordingly, the captioned petition stands disposed of. PREETI PAREWA (DHJS) JOINT REGISTRAR (JUDICIAL) AUGUST 28, 2025/ab The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 01/09/2025 at 12:14:07