Indian Oil Corporation Limited v. Allied Concern
$~O-47 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P.(MISC.)(COMM.) 715/2025 INDIAN OIL CORPORATION LIMITED .....Petitioner Through:
Mr.
Som Raj Choudhuiy and Ms.Shrutee Aradhana, Advocates.
versus ALLIED CONCERN .....Respondent Through:
Ms. Akanksha Rai and Mr. Hasan Raza Khan, Advocates.
CORAM:
HON'BLE MR. JUSTICE PURUSHAINDRA KUMAR KAURAV
O R D E R
% 18.09.2025 1.
The petitioner in the instant petition prays for the following reliefs:- "a) extension of two months to the present Arbitral reference for completion of the Arbitration Proceedings; and/ or b) any other relief deemed fit by this Hon'ble Court." 2.
It is pointed out that on 01.09.2025, award has been passed, which appears to have been circulated on 03.09.2025. 3.
It be noted that on 01.09.2025 itself, the Court had directed for issuance of notice.
4.
Reserving all rights and contentions of the parties regarding the validity of award etc. On merits, the Court deems it appropriate to regularize the period w.e.f. 08.07.2025 to 01.09.2025.
The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 24/09/2025 at 12:58:26
5.
Ordered accordingly.
6.
The instant petition stands disposed of.
PURUSHAINDRA KUMAR KAURAV, J SEPTEMBER 18, 2025 Nc/sph The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 24/09/2025 at 12:58:26