Indraprastha Power Generation v. D.S.E.B. Employees Union & ANR
$~9 * IN THE HIGH COURT OF DELHI AT NEW DELHI CM Nos.3833-34/2021 in + W.P.(C) 13042/2006 INDRAPRASTHA POWER GENERATION .....Petitioner Through :
Mr. Vinay Sabharwal, Adv.
versus D.S.E.B. EMPLOYEES UNION & ANR .....Respondents Through :
None.
CORAM:
HON'BLE MR. JUSTICE RAJIV SHAKDHER
O R D E R
% 03.02.2021 [Court hearing convened via video-conferencing on account of COVID-19] CM Nos.3833-34/2021 1.
Issue notice to the non-applicants/respondents via all permissible modes.
2.
In effect, via CM No. 3833/2021, the petitioner seeks recall of the order dated 05.04.2019 whereby the writ petition was dismissed for nonprosecution. Via CM No. 3834/2021, the petitioner seeks condonation of delay in moving the application for restoration i.e. CM No. 3833/2021. 3.
It is averred that the writ petition was admitted on 07.12.2006 and, thereafter, on successive dates, it was listed only in 2019, albeit, in the regular category. It is submitted that because of the long gap, the matter was, somehow, missed by the counsel for the petitioner. 4.
List the captioned applications on 12.05.2021. RAJIV SHAKDHER, J FEBRUARY 3, 2021 aj Click here to check corrigendum, if any By:VIPIN KUMAR RAI 23:45:54