Kiran Infra Engineers Limited v. Northern Railways
$~56 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P.(MISC.)(COMM.) 801/2024 KIRAN INFRA ENGINEERS LIMITED .....Petitioner Through:
Mr. Devanshu Chauhan, Advocate.
versus NORTHERN RAILWAYS .....Respondent Through:
Mr. Sushil Kumar Pandey, SPC, Ms.
Richa Pandey and Ms. Neha Yadav, Advocates for UoI.
CORAM:
HON'BLE MR. JUSTICE SUBRAMONIUM PRASAD
O R D E R
% 08.10.2024 I.A. 41717/2024 (Exemption) Allowed, subject to all just exceptions.
O.M.P.(MISC.)(COMM.) 801/2024 1.
This Petition under Section 29A(4) and 29A(5) of the Arbitration and Conciliation Act, 1996 has been filed by the Petitioner for extending the mandate of the Sole Arbitrator.
2.
Material on record indicates that the Sole Arbitrator was appointed by this Court on 06.05.2022. It is stated that the mandate of the Sole Arbitrator was further extended till 19.08.2024 for making the award. 3.
It is stated by the learned Counsel for the Petitioner that final arguments have been advanced and the matter was reserved for pronouncement of award on 12.07.2024.
4.
The present petition has, therefore, been filed seeking extension of The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 15/10/2024 at 12:04:28
mandate of the Sole Arbitrator.
5.
In view of the facts of the present case, this Court is inclined to extend the mandate of the Sole Arbitrator till 31.03.2025 so that the award can be pronounced.
6.
The Petition is disposed of, along with the pending applications, if any.
SUBRAMONIUM PRASAD, J OCTOBER 8, 2024 S. Zakir The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 15/10/2024 at 12:04:28