$~36 * IN THE HIGH COURT OF DELHI AT NEW DELHI + CRL.REV.P. 260/2014 SNAM ELECTRICALS PVT LTD & ANR .....Petitioners Through:

Mr. Kamal JS Mann, Mr. Manish, Advs.

versus SHREE NURSINGASAHAY MUDUNGOPAL ENGINEERS PVT LTD .....Respondent Through:

Mr. Jagdeep Sharma, Sr. Adv. with Mr. Kartikay Sharma, Ms. Rishika, Advs.

CORAM:

HON'BLE MR. JUSTICE JASMEET SINGH

O R D E R

% 13.02.2025 CRL.M.A. 4630/2025 1.

This is an application file by the applicant/revisionist No. 2 seeking permission to withdraw the revision petition. 2.

As per the revisionist No. 2, there is an amount of Rs. 11 lakhs lying deposited with the learned MM in the form of FDR. 3.

During the course of the hearing, the parties have agreed that an amount of Rs.

lakhs be released to the respondent through counsel/nominee/AR and the interest accrued on the amount of Rs. 11 lakhs shall be shared between the revisionists and the respondent in the ratio of 75% and 25% i.e. 75% of the interest accrued on Rs. 11 lakhs shall be paid to the revisionists and 25% of the interest accrued on Rs. 11 lakhs shall be paid to the respondent.

4.

It is ordered accordingly. The amount maybe paid to the revisionists The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 14/02/2025 at 12:21:53

and the respondent through counsel/self or duly authorized agent. 5.

The needful shall be done expeditiously and in any case not later than 2 days from today.

6.

With these directions, the application is allowed and disposed of. CRL.REV.P. 260/2014 7.

In view of the order passed above, the revision petition stands disposed of.

8.

The next date of hearing i.e. 12.03.2025 stands cancelled. 9.

Order Dasti under the signature of Court Master. JASMEET SINGH, J FEBRUARY 13, 2025/DM Click here to check corrigendum, if any The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 14/02/2025 at 12:21:53