High Court of DelhiO.M.P.(MISC.)(COMM.)/828/2024

Reliance Infrastrcuture Limited v. Aravali Power Company Private Limited

2024-10-18Hon'Ble Mr. Justice Sachin Datta2 pages

$~50 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P.(MISC.)(COMM.) 828/2024 RELIANCE INFRASTRCUTURE LIMITED .....Petitioner Through:

Mr. Ankur Kashyap, Mr. Aditya Panda, Mr. Aman Bajaj and Mr.

Akshay S., Advocates.

versus ARAVALI POWER COMPANY PRIVATE LIMITED .....Respondent Through:

Mr. Adarsh Tripathi, Mr. Vikram Singh Baid and Mr. Ajitesh Garg, Advocates.

CORAM:

HON'BLE MR. JUSTICE SACHIN DATTA % 18.10.2024

O R D E R

1.

The present petition under Section 29A(5) of the Arbitration and Conciliation Act, 1996 (hereinafter 'the A&C Act') has been filed by the petitioner seeking extension of time for completion of arbitral proceedings and making of arbitral award.

2.

It is submitted by the learned counsel for the petitioner that the arbitral proceedings are at the stage of final arguments. It is pointed out that on the previous occasions, appropriate extensions have been granted by this Court upon a petition under Section 29A(4) of the A&C Act being filed by the petitioner.

3.

It is submitted that the arbitration proceedings have been protracted in view of the nature of the matter and the time consumed by the parties in adducing their respective evidence, and completing their arguments. 4.

Learned counsel for the respondent does not oppose the present petition The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 03/07/2025 at 04:22:34

seeking requisite extension of time for completion of arbitral proceedings and making of arbitral award. He further submits that learned Sole Arbitrator be also directed to grant some additional time to the respondent to complete its arguments. Needless to say, the respondent shall be at liberty to make a request in this regard to the learned Sole Arbitrator, who shall consider any such request on its own merit. However, taking note of the joint request for requisite extension of time, the time period of completion of arbitral proceedings and making of the arbitral award is extended till 31.05.2025. 5.

The present petition stands disposed of.

SACHIN DATTA, J OCTOBER 18, 2024/at The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 03/07/2025 at 04:22:34