M/S Greentech Power Pvt Ltd v. M/S Ntpc Vidyut Vyapar Nigam Ltd & ANR
$~ * IN THE HIGH COURT OF DELHI AT NEW DELHI 59.
+ O.M.P. 394/2012 GREENTECH POWER PVT LTD ..... Petitioner Through: Mr. Ashok Chhabra, Advocate with Mr. Pawan Kumar Mittal, Advocate.
versus M/S NTPC VIDYUT VYAPAR NIGAM LTD & ANR ..... Respondent Through: Mr. Bharat Sangal, Ms. Vidhushi Garg Advocates.
CORAM: JUSTICE S. MURALIDHAR
O R D E R
% 17.10.2016
1. The arbitral proceedings are stated to be at the final stage. It is permissible for the Petitioner to file a copy of this very petition as an application before the learned Arbitrator. The interim order dated 27th April, 2012 is directed to continue till such time the learned Arbitrator varies or modifies the said order under Section 17 of the Arbitration and Conciliation Act, 1996 in accordance with law.
2. The petition is disposed of.
S. MURALIDHAR, J OCTOBER 17, 2016 mg