$~4 * IN THE HIGH COURT OF DELHI AT NEW DELHI + CONT.CAS(C) 1686/2024 SUMIT .....Petitioner Through:

Mr. Sumit Rana, Advocate.

versus MUNICIPAL CORPORATION OF DELHI AND ORS....Respondents Through:

Mr. Sanjeev Sabharwal, SC for MCD with Ms Shweta Singh, Advocate for MCD.

Mr. Vardhaman Kaushik, Mr.

Prithiviraj Dey and Ms. Kavya Shukla, Advocates.

CORAM:

HON'BLE MR. JUSTICE AMIT SHARMA

O R D E R

% 01.12.2025 1.

This hearing has been done through hybrid mode. 2.

The present petition under Sections 2(b) and 12 of the Contempt of Courts Act, 1971, read with Article 226 of the Constitution of India seeks the following prayers:

"i) Initiate appropriate civil contempt proceedings against the respondents and punish the Contemptors / respondents accordingly;

ii) Pass appropriate orders / directions to the Contemptor / Respondent no. I and 2 to comply / directions passed by this Hon'ble High Court of Delhi vide order dated 16.04.2024; iii) Pass such further or other orders which this Hon'ble Court may deem fit and proper in the circumstances of the case." 3.

Status report dated 08.03.2025 has been filed on behalf of the MCD, wherein it has been recorded as under:

The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 04/12/2025 at 11:06:40

"10.

That pursuant to aforesaid demolition / sealing orders already passed in respect of the subject properly the Building Department -II of South Zone - MCD has also tried /taken / carried out the necessary action as per details given herein below:

S.No.

Date of Action Action Taken 1.

03/05/2024 Action could not be taken due to shortage of time.

2.

31/05/2024 Upon availability of police force, 02 RCC panels demolished and cut at Stilt floor slab, further defaced all floors and internal brick walls also demolished.

After taking the said action the entire building has been sealed by putting seal at 01 point at the entrance of the building at Stilt floor.

The Photographs taken during the aforesaid demolition/sealing action are annexed herewith as Annexure-G (Colly)."

4.

In view of the above, learned counsel for the petitioner does not wish to press the present petition.

5.

The present petition is disposed of as not pressed. 6.

Pending application(s), if any, also stands disposed of. AMIT SHARMA, J DECEMBER 01, 2025/bsr/db The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 04/12/2025 at 11:06:40