Rudra Dev & ANR. v. Vardhman Estate & Developers Pvt. Ltd.
$~2 *
IN THE HIGH COURT OF DELHI AT NEW DELHI
+ ARB.P. 90/2015 RUDRA DEV & ANR ..... Petitioners Through Mr.Shanul Kadian, Adv.
versus VARDHMAN ESTATE & DEVELOPERS PVT. LTD.
..... Respondent Through Mr.Amit Bhatia, Adv.
CORAM:
HON'BLE MR. JUSTICE MANMOHAN SINGH
O R D E R
% 11.05.2016 The present petition has been filed by the petitioner under Section 11 of the Arbitration and Conciliation Act, 1996 for appointment of an Arbitrator.
Heard. With the consent of the parties, the prayer made in the petition is allowed.
As agreed, the matter is referred to the Delhi International Arbitration Centre ('DAC') who will appoint an Arbitrator in accordance with the provisions of the Act.
The Arbitrator to adjudicate the disputes arising out between the parties as mentioned in the present petition. The parties are also allowed to file their respective claims and counter-claims before the Arbitrator.
The arbitration shall take place under the aegis of DAC. The Arbitrator shall ensure the compliance of the provisions of Arbitration and
Conciliation (Amendment) Act, 2015 before commencing the arbitration. The fees of the learned Arbitrator shall be in terms of the Delhi International Arbitration Centre (Administrative Cost Arbitrator's Fees) Rules. The parties to appear before the DAC on 26th May, 2016. The petition is accordingly disposed of.
Copy of this order be given dasti to the learned counsel for the parties and a copy thereof be delivered to the Additional Coordinator, DAC forthwith.
MANMOHAN SINGH, J.
MAY 11, 2016/ka