Vm Construction v. Union Of India
$~O-55 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P.(MISC.)(COMM.) 873/2024 VM CONSTRUCTION .....Petitioner Through:
Mr. Ankit, Advocate (through VC).
versus UNION OF INDIA .....Respondent Through:
Ms. Aakanksha Kaul, Mr. Aman Sahani and Ms. Ashima Chopra, Advocates for UOI.
CORAM:
HON'BLE MR. JUSTICE PURUSHAINDRA KUMAR KAURAV
O R D E R
% 08.05.2025 1.
In the interest of justice and for the reasons explained in the petition, the same is allowed in terms of prayer 'A', which is reproduced as under: "A. Pass appropriate orders under the provisions of Section 29 A (4) and extend the period of Arbitration Case No. DIAC/2701/01-20 for further nine months from 08.11.2024 in the interest of Justice." 2.
Accordingly, the petition stands disposed of. PURUSHAINDRA KUMAR KAURAV, J MAY 8, 2025 ssc Click here to check corrigendum, if any The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 01/07/2025 at 16:31:19